Activity Network Diagram
Description : An activity network Diagram is also called: arrow diagram, network diagram, activity chart, node diagram, CPM (critical path method) chart or PERT (program evaluation and review technique) chart .
When to Use:
When scheduling and monitoring tasks within a project or process with several dependant tasks and resources.
When you know the steps of the project or process, their sequence and how long each step takes.
When your project schedule is critical. There is a serious consequences for
completing the project late or a significant advantage to completing the
project early.
Drawing the Activity Network Diagram Procedure :
1. List all the necessary tasks in the project or process. One
convenient method is to write each task on the top half of a notecard or
a sticky note. Then across the middle of the card, draw a horizontal arrow
pointing right.
2. Determine the correct sequence of the tasks. Do this by asking three questions for each task:
o Which tasks must happen before this one begins?
o Which tasks can be done at the same time as this one?
o Which tasks should happen immediately after this one?
It can be useful to create a table with four columns prior tasks, this task, simultaneous tasks, following tasks.
3. Diagram the network of tasks. If you are using sticky notes or notecards, arrange them in sequence on a large piece of paper. For the activity network diagram, time should flow from left to right and concurrent tasks should be vertically
aligned. Leave space between the cards.
4. Between each two tasks, draw circles for events. An event
marks the beginning or end of a task. Thus, events are nodes that
separate tasks.
5. Look for the three common problem situations noted below. Redraw them
using dummies or extra events. Characterize a dummy with a dotted line arrow. Dummies are not real
tasks.
Problem situations:
Two simultaneous tasks start and
end at the same events.
Solution:
Use a dummy and an extra event to separate them. In Figure 1 , event 2
and the dummy between 2 and 3 have been added to separate tasks A and
B.
Task C cannot start until both tasks A and B are
complete; a fourth task, D, cannot start until A is complete, but need not wait for B. (See Figure 2.)
Solution: Use a dummy between the end of task A and the beginning of task C.
A second task can be started before part of a first
task is done.
Solution:
Add an extra event where the second task can begin and use multiple
arrows to break the first task into two subtasks. In Figure 3, event 2
was added, splitting task A.
7. Determine task timesthe best estimate of the time that each
task should require. Use one measuring unit (hours, days or weeks)
throughout, for consistency. Write the time on each tasks arrow.
8. Within the Activity Network Diagram determine the critical path, the longest path from the beginning to the end of the project. Mark the critical path with a
heavy line or color. Calculate the length of the critical path: the sum
of all the task times on the path.
9. Calculate the earliest times each task can start and finish, based on how long preceding tasks take.
These are called earliest start (ES) and earliest finish (EF).
Start with the first task, where ES = 0, and work forward.
Finish the Activity Network Diagram by drawing a square divided into four quadrants, as in Figure 4. Write the ES in the top left box and the EF in the top right.
For each task:
o Earliest start (ES) = the largest EF of the tasks leading into this one
o Earliest finish (EF) = ES + task time for this task
After reviewing the Activity Network Diagram click here to see other Total Quality Management Tools










